Opened in 1840, the viaduct carries around 400 trains a day high across the Greater Manchester landscape. The time will come later this year for the structure to be given some TLC.
Last year, Network Rail started the project to remove overgrowing vegetation, clean away graffiti and carry out extensive repairs to the viaduct’s 11 million bricks. So far, 23 of the viaduct’s 26 spans have received the VIP treatment.
The 550-metre long, 34-metre tall viaduct crosses the M60 and River Mersey. Engineers will abseil down the viaduct above the motorway to carry out work to the remaining arches.
The next aspect of the work will require the M60 to be closed each night for almost two weeks. For 13 nights between Monday February 17 and Sunday March 2 the road will be closed in both directions from Junction 1 to Junction 27.


Rob Stephens, principal route engineer for the North West route, said: “Stockport Viaduct is an important piece of cultural heritage for the railway and the Stockport community. We are proud to be responsible for its upkeep. The final stage of the project will take place this February, as we want to make sure the night time road closure causes as little inconvenience as possible for the people of Stockport.
“The recent work means the overall appearance of the viaduct is much improved, but it also reduces the risk of damage caused by overgrown vegetation and graffiti.
“Managing plant growth on viaducts such as this is important in maintaining train performance as trees and shrubs can obscure signals and interfere with the overhead lines that power trains.”
Cllr Grace Baynham, cabinet member for Parks, Highways and Transport Services, said: “Stockport Viaduct is an iconic feature of our town and it is great that Network Rail has been carrying out the restoration of this much loved structure. With the £1billion regeneration of our town centre continuing apace, it’s even more important that our historical, listed, landmarks look their absolute best.
“I’m sure our residents and visitors have seen the improvement in the areas that have already been completed. We appreciate everyone’s patience while this vital final section of the work is completed.”