Bury drivers brace for months of road closures and temporary traffic lights in 2026
Roadworks to complete a £5.7m Bee Active travel scheme in Bury are set to continue for much of 2026.
The council has published a list of the works, including months of road and lane closures on Market Street and Rochdale Road, involved in phase 2 of the Fishpool and Pimhole scheme.
The work programme is split into 12 individual projects, each focussed on specific roads and streets within in Fishpool and Pimhole.


A spokesman for Bury council, said: “The scheme will improve connectivity to Bury town centre and other local facilities, making it safer and easier for people to walk, wheel or cycle for local journeys.
“This will allow people to reduce car trips and choose healthier, greener ways to travel.” A public notice order published by the council states Market Street will be subject to closures from Monday, January 5 as the second phase of theBee Active travel scheme brings new cycle facilities and signalled crossings to the area along with resurfacing works.
The proposed order will remain in force for ‘a period of up to 18 months’ but that the anticipated works should take ‘up to 24 weeks’. The council said before works start they will install advance warning signs at the roadside and if a full road closure is required, a diversion route will be signed.
Access to Bury College and pedestrian access to Market Street will be maintained at all times. Also in January and February work will go ahead on a one-way routing, with no access for vehicles from Parker Street to Heywood Street.


Signalised parallel crossings will also be installed. There will be lane closures on Heywood Street, two-way temporary traffic lights and the closure of Parker Street at its junction with Heywood Street for approximately eight weeks.
Access to the mosque and businesses on Parker Street will be maintained from Lord Street. January and February will see works in the Albert Street area for footpath widening.
The Albert Street/Rochdale Road junction will be permanently closed with motorists told to expect lane closures on Rochdale Road.
From March 2026 onwards the work done will include an upgraded junction, removal of roundabout and signalised crossing at Market Street and Wellington Road.
Also at that time the junction will be upgraded and the road resurfaced at Manchester Road and Parkhills Road and a signalised crossing, uncontrolleddropped crossings and a raised road table installed at Manchester Road and Gigg Lane.
The Heywood Street main junction will also be improved with a crossing installed in the spring of 2026.
Motorists can expect lane closures on Rochdale Road and Heywood Street, three-way temporary traffic lights and the full road closure at Bond Street/Rochdale Road junction for two weeks.