Manchester city council has announced a programme of works on roads outside the city centre. The development is part of work taking place around the Ancoats area of Manchester. 

Work started on May 13 on improvements to cycleways, pedestrian crossings, carriageways, footpaths, and traffic signals at the junction of Oldham Road with Poland Street and Radium Street. The council estimates the work will be completed in Autumn 2024.  

Hide Ad
Hide Ad

The council have also announced that the work will be divided up into five phases. The first of these is expected to take two weeks. 

Full timeline for Ancoats Roads work

Work has started on roads in AncoatsWork has started on roads in Ancoats
Work has started on roads in Ancoats | Adobe Stock

Phase One (approximately two weeks)

One traffic lane will be closed in both directions on Oldham Road, between Bengal Street and Poland Street.

Phase Two (approximately seven weeks)

Cycle lane and one general traffic lane closed outbound on Oldham Road between Radium Street and Poland Street.

Phase Three (approximately three weeks)

One inbound lane partially closed on Oldham Road at the Poland Street junction

Hide Ad
Hide Ad

Phase Four (phase length to be determined)

Radium Street fully closed at the junction with Oldham Road. Bus lane suspended at this point. A signed diversion will be in place.

Phase Five (phase length to be determined)

Full lane closures in both directions on Oldham Road overnight (on separate dates from each other). Signed diversions will be in place.

Councillor Tracey Rawlins, Executive Member for Environment and Transport said: “As part of our ongoing work across the city we are looking at ways to make journeys safer for all our residents and improve transport links along key transport arteries. The Oldham Road corridor is an extremely busy and well-used stretch of road, providing a link to Ancoats and the city centre, which is why it’s important that this work takes place. Updates will be provided as the work progresses, and as always I’d advise people to plan their journey in advance to make sure any disruption can be minimised.”