Massive £3m contract awarded for project to pave way for new Northern Gateway employment park

A contract for nearly £3m has been awarded for a ‘western access’ project to pave the way for the massive Northern Gateway employment park.

Bury council’s cabinet this week allocated £2.83m to cover the finalising an outline business case for the scheme. In February this year, the council approved the appointment of Balfour Beatty UK as the western access scheme’s main construction contractor.

The Northern Gateway project is set to become one of the largest employment hubs in the region, driving substantial investment and up to 10,000 jobs into Greater Manchester. It also promises new homes straddling areas of Bury and Rochdale along the M60, M62 and M66 corridors.

It features proposals for 6.5 million sqft of industrial space for the advanced manufacturing, industrial, and logistical sectors. Outline planning permission for the scheme is currently being determined by both Bury and Rochdale councils.

Northern Gateway is part of the Places for Everyone development plan and is the largest designated development site in the Atom Valley Mayoral development zone. A report to Bury council cabinet gave details of the the western access scheme which will see improvements to the Pilsworth Road corridor in Bury.

placeholder image
LDRS

The report, said: “It is a cross boundary scheme with Rochdale Council. It will provide the necessary off-site, highway and transportation infrastructure required to access the early development phases of the Northern Gateway investment zone.

“The construction of the western access scheme will therefore support the creation of high quality, employment floor space, including space within the advanced manufacturing and foundational sectors.”

The report said the western access outline business case would identify a preferred option for the scheme, produce associated concept designs and an updated scheme budget estimate. The report added: “Importantly, the outline business case will also provide the robust strategic, economic and financial cases for the scheme.

“In turn this will then provide the firm foundation for the development of the subsequent full business case, which will confirm detailed designs and costings.”

The report said that if the funding was not approved, it would risk investment zone grant funding totalling £1.5m not being fully utilised, with the funding being reallocated elsewhere in Greater Manchester.

The report, said: “This presents a high risk to the delivery of the Western Access scheme and the Northern Gateway investment zone.”